A shutdown date may be fixed long before every replacement block is ready. If one custom shape is missing, damaged or made to an outdated drawing, the installation team may be unable to complete that area. Buying early helps, but a reliable plan also needs a clear definition of when the material is actually ready to use.

Refractory preassembly in the Dezhong workshop. Agree the required assembly scope before scheduling acceptance.
For fused cast alumina-zirconia-silica (AZS) blocks, plan backwards from the date the installation team needs the material at the plant. Do not treat a factory completion date or a vessel arrival estimate as that date.
This guide covers procurement readiness for a planned shutdown or cold repair. Furnace shutdown, installation and heat-up procedures remain the responsibility of the qualified project team.
Work backwards from the installation date
Ask the project team when each furnace area needs its blocks, not only when the furnace will stop. Then work back through site receipt, transport, dispatch and factory release. The table runs backwards from use to production; it is a planning checklist, not a fixed delivery calendar.
|
Milestone |
What must be ready |
|
Installation need date |
Required blocks identified and released for use at the plant, with time for receiving checks. |
|
Arrival at the plant |
Inland delivery, unloading arrangements, document checks and contingency time included. |
|
Export dispatch |
Acceptance closed, balance received, packing complete and shipment arrangements confirmed. |
|
Factory acceptance |
Inspection scope, reviewer availability, reports and any recheck time agreed. |
|
Production release |
Final drawings approved and the agreed advance payment received; order schedule confirmed. |
Assign one owner, a target date and completion evidence to each milestone. Separate confirmed dates from estimates. Review the whole schedule when one date changes, and avoid counting the same inspection or packing allowance twice.
Allow a project-specific buffer for foreseeable uncertainty. Its size should reflect the route, order complexity and the consequences of a missing item, rather than a universal number of extra days.
Close drawing and acceptance gaps early
A grade name and total tonnage do not define a complete custom order. Reconcile the current drawing revision with block numbers, quantities, orientation, special openings and the agreed material and dimensional requirements. Identify any mating dimensions that the furnace designer must confirm.

Customers and Dezhong personnel reviewing refractory blocks at the factory. Inspection arrangements are agreed for each order.
Detailed and assembly drawings have different purposes in furnace engineering. For purchasing, the practical requirement is a single approved production basis shared by buyer and supplier, with a clear record of later changes.
Technical reference:HORN on refractory design and assembly documentation
Before production, agree which inspections and reports are required, who may accept the goods and how open points will be closed. Book the review window early. A photograph of finished blocks is not a substitute for the agreed acceptance record.
Keep production time separate from transit time
At Dezhong, formal scheduling begins after final drawing approval and receipt of the agreed advance payment. Normal production for these customized fused cast orders is around 40 days, subject to the confirmed order schedule. This is not a promise of arrival at your plant within 40 days.

Dezhong export case with film, securing bands, shipping marks and a packing list. Labels shown belong to the photographed order.
After agreed acceptance is completed and the balance is received, we arrange export packing and delivery to the agreed port for shipment. Packing uses fumigated wooden pallets or cases, plastic film, steel bands, labels, shipping marks and a packing list as agreed. The advance percentage and port are confirmed per order.
Confirm the route and current sailing schedule with the responsible logistics party. Include destination clearance and inland delivery in the arrival plan. Ocean transit is only one part of the journey; an estimated port arrival is not installation readiness.
Technical reference:Maersk on checking transit times for the required route